Henderson Construction Project


 

Click on a thumbnail photo below to enlarge the picture.

 

January 6, 2003

January 16, 2003

January 24, 2003

Interior demolition of Henderson.

Roof removal from
Henderson.

Roof completely removed.

     

January 27, 2003

February 3, 2003

February 13, 2003

Second floor brick removed.

Structural shoring for stone masonary.

Interior conduit installed below grade.

     

March 3, 2003

March 21, 2003
March 27, 2003

Basement floor being prepared for concrete.

Elevator shaft construction & continued work on basement floor.
Basement, elevator, and exterior wall progress.
   
April 4, 2003
April 15, 2003
April 29, 2003

 

First floor construction, including elevator and concrete flooring.
First floor exterior walls, continued work on basement floor.
Installation of new water main. Construction begins on second floor.
   
May 6, 2003
May 14, 2003
May 23, 2003

 

 

Third floor construction. Basement ductwork in place.
Installation of roof trusses.
Installation of roof trusses. Roof sheathing in progress.
   
May 27, 2003
June 5, 2003
June 9, 2003

Shingle & roof work. Water line progress.
Shingle & roof work.
Basement electrical, ductwork, plumbing progress on basement through 2nd floors. Roof progress, stairwell steps.
   
June 16, 2003
June 23, 2003
July 3, 2003

 

Exterior progress. Elevator track installation.
Preparation for brick installation.
Brick installation. Ground floor progress.
     
July 9, 2003
July 16, 2003
July 25, 2003

 

 

Room and hallway progress. Access ramp construction.
Exterior brick work. ADA access ramp excavation. Interior ground floor progress.
Exterior views. Game room and hallway progress.
     
July 31, 2003
August 4, 2003
August 11, 2003
 
Room and hallway progress.
Fitness room.
Recreation room progress.
"A" level view from main entrance.
1st floor hallway progress.
Room setups.
3rd floor hallway.
Sidewalk installation.

 