Donner Residents,
The Donner Fire Suppression installation has progressed over the past week.
They have the 1st and 2nd floor hallway ceilings framed along with all the
2nd floor room bulkheads.
The piping has been installed in the resident rooms on the entire 3rd floor.
The system has been leak checked. The main piping has been installed in the
2nd floor hallways.
Rycon will be installing ceiling frame work in resident rooms on the 1st
floor as well as installing drywall on the 3rd floor hallway ceilings next
week.
Ryco, the sprinkler contractor, will be installing sprinkler lines into
resident rooms on the 2nd floor. Ryco asked that the residents remove all
items from their top closet shelves in the rooms scheduled next week for pipe
installation as well as relocating their bath towels from the towel racks for
a week. Ryco will be installing sprinkler heads in each closet where the top
shelf is located.
I want to thank all of you for your continued cooperation and patience.
Sincerely,
Thom Thornton
Housing Services Facility Coordinator
----------------------------------------------------------------