Subject: Suppresion System Installation Update
   Date: Fri 10/11/2002 1:16 PM
   From: Housing <univhous@andrew.cmu.edu>
     To: Boss-Residents@wgs.housing.cmu.edu <Boss-Residents@wgs.housing.cmu.edu>
     	 McGill-Residents@wgs.housing.cmu.edu <McGill-Residents@wgs.housing.cmu.edu>


Dear Residents of Boss and McGill,

The following is an updated schedule for next week provided to me by the
project supervisor.

Monday the goals are to install the grid work for the ceiling in the ground
floor of Boss, grid work 1st - 2nd - 3rd floors of Boss.

Tuesday the goals are to install the grid work in the ground floor of McGill

Wednesday the goals are to begin the grid work on all floors of McGill

Thursday the goals are to continue the grid installation on all floors of
McGill

Friday The goal is to wrap up the grid installation in McGill.

Please keep in mind that on occasion there can be circumstances that occur
that make these workers deviate from this schedule.

Thank you for your cooperation with this very important project.

Steve Gergely
Facility Coordinator


    ----------------------------------------------------------------
    *   For additional information about Housing Services,         *
    *   please visit our web site at:                              *
    *                                                              *
    *                 http://www.housing.cmu.edu/                  *
    ----------------------------------------------------------------





| Return to Announcements Page |